If 15 workers complete a task in 12 days, how many days will 20 workers take at the same rate?
Correct Answer: C. 9 days
Practice this MCQ with options, instant answer checking, explanation, exam-wise filters, next/previous navigation and shareable result image.
This question is useful for exam preparation because it provides direct multiple-choice practice with options, answer checking and explanation.
Correct answer: C. 9 days