A can finish a task in 12 days and B in 18 days. Working together, they finish it in:

Practice this MCQ with options, instant answer checking, explanation, exam-wise filters, next/previous navigation and shareable result image.

Question ID #17190

A can finish a task in 12 days and B in 18 days. Working together, they finish it in:

Correct Answer: B. 7.2 days

A can finish a task in 12 days and B in 18 days. Working together, they finish it in: - MCQ Explanation

This question is useful for exam preparation because it provides direct multiple-choice practice with options, answer checking and explanation.

Correct answer: B. 7.2 days