8 workers finish a job in 8 days. How long will 16 workers take? Apply it in the context of AFCAT Arithmetic and Number System Test.
Practice this MCQ with options, instant answer checking, explanation, exam-wise filters, next/previous navigation and shareable result image.
Question ID #21873
8 workers finish a job in 8 days. How long will 16 workers take? Apply it in the context of AFCAT Arithmetic and Number System Test.
Correct Answer: A. 4 days
8 workers finish a job in 8 days. How long will 16 workers take? Apply it in the context of AFCAT Arithmetic and Number System Test. - MCQ Explanation
This question is useful for exam preparation because it provides direct multiple-choice practice with options, answer checking and explanation.
Correct answer: A. 4 days