10 workers finish a job in 9 days. How long will 20 workers take? Apply it in the context of AFCAT Final Grand Mock Test.
Practice this MCQ with options, instant answer checking, explanation, exam-wise filters, next/previous navigation and shareable result image.
Question ID #22592
10 workers finish a job in 9 days. How long will 20 workers take? Apply it in the context of AFCAT Final Grand Mock Test.
Correct Answer: D. 4.5 days
10 workers finish a job in 9 days. How long will 20 workers take? Apply it in the context of AFCAT Final Grand Mock Test. - MCQ Explanation
This question is useful for exam preparation because it provides direct multiple-choice practice with options, answer checking and explanation.
Correct answer: D. 4.5 days